1.        The Bloomington Bike Company produces two models: the Basic and the Supra. Herb Hoosier, the owner, plans to assemble 10 Basics and 15 Supras in each week during periods 4 to 8. Product structure trees for each bike are shown below:

                                                        B                                                  S



                                    X        M                            W                 K(2)                         F

                   








                           F

                                                                            W(2)                            Q

Develop a materials requirement plan (MRP) for component parts K and W over the next eight weeks. Data on all lead times, current inventory and ordering rules are given below: Scheduled receipts are: Period 1: 20 B's, 18 W's; Period 2: 20 S's, 15 F's. A sample MRP table is provide below.


ITEM

LEADTIME (WKS)

ON HAND

LOT-SIZING RULE

B

2

5

Lot-for-lot

S

2

2

Lot-for-lot

X

1

5

Multiples of 25

W

1

2

Multiples of 12

F

1

10

Multiples of 30

K

1

3

Lot-for-lot

Q

1

15

Multiples of 30

M

1

0

Lot-for-lot


1

2

3

4

5

6

7

8

Gross requirements

Schedule receipts

Projected on hand

Net requirements

Planned order receipt

Planned order release


2.        A firm makes car seats for an automaker in two varieties: leather and fabric. The standard labor-hours for these are 1.2 and 1.0 hours, respectively. The seats are made in two work centers, sewing and assembly, where the average percentage of work has been 55 percent for sewing and 45 percent for assembly. The following schedule for the next six weeks is given.  


Week

1

2

3

4

5

6

Leather

15

20

18

21

15

13

Fabric

65

60

62

59

65

67


a)         Using the CPOF (Capacity Planning Using Overall Factors) approach, calculate the labor-hours needed in each of the two work centers in each week.

b)        Suppose the following information is given. Using the capacity bills approach, calculate the labor-hours needed in each of the two work centers in each week.

Work Center

Time (hours/unit)

Leather

Fabric

Sewing

0.7

0.6

Assembly

0.5

0.4

Total

1.2

1.0


3.        A manufacturing facility produces two types of a product: Standard and Deluxe. The process flow for both types of production is shown in the following chart. Both types are first processed through steps A1 and A2. The Standard then goes through steps A3 and A4 while the Deluxe is processed through steps A5, A6, and A7. Both types finish at A8. The numbers in parentheses indicate the minutes it takes for that activity to process a single unit.














a)         Which step is the bottleneck for the Standard products? Which step is the bottleneck for the Deluxe products?

b)        What is the capacity (measured as units per hour) of the facility to process the Standard products? What is the capacity to process the Deluxe products?

c)         If 60% of the products are Standard and 40% are Deluxe, what is the average capacity (measured as units per hour) of the facility?

d)        Suppose the actual throughput of the facility is 3.2 units per hour. Again, 60% of the products are Standard and 40% are Deluxe. What is the utilization of each step (A1-A8)?


Screen Shot 2018-04-01 at 4.47.25 PM.png

Screen Shot 2018-04-01 at 4.47.25 PM.png

5‘ Assignment 3,2 Home Insert Design Layout References Mailings
X l ._ .7 .7 7 -
v w Calibri Bod v 12 v AA Av A” v :2 v g: . a:v E A; F
( Y) a ‘1 r lz l 1] AaBchDdEe AaEbCEDdEe AaBchD< AaBchDdEt AaBb( Aaabcmdte ' 0
Paste Normal No Spacing Heading 1 Heading 2 Title Subtitle Styles
6 7 7777 77 7 7 7 7 77 7 7777 7 77 777 7 77 7 7 77 7 77 77 7 7 Pane “gum...“ u 1. The Bloomington Bike Company produces two models: the Basic and the Supra. Herb Hoosier, the owner, plans to assemble 10 Basics and 15 min each week durlng periods 4 to B.
Product structure trees for each bike are shown below: B s
l
M w K ) F ‘
3:: Fabric | 65 a) Using the CPOF (Capacity Planning Using Overall Factors) approach, calculate the labor-
hours needed in each of the two work centers in each weelc b) Suppose the following information is given. Using the capacity bills approach, mlculate
the labor-hours needed in each of the two work centers in each week. Time (hours/unit) Work Center Leather Fabric
Sewi ng 0.7 0.6
W12) Total 1.2 1.0 Develop a materials requirement plan (MRP) for component parts K and W over the next
eight weeks. Data on all lead times, current inventory and ordering rules are given below:
Scheduled recelpts are: Period 1: 20 5’5, 18 W's; Period 2: 20 S’s, 15 F's. A sample MRP table is provide below. 3. A manufacturing facility produces two types of a product: Standard and Deluxe. The process
flow for both types of production is shown in the following chart. Both types are first l l l l ‘ Assembly 0.5 0.4 l l l processed through steps A1 and A2. The Standard then goes through steps A3 and A4 while centers, sewing and assembly, where the average percentage of work has been 55 percent roducts are Standard and 40% are Deluxe. What is the utilization of each ste A1—A8 ?
for sewing and 45 percentfor assembly. The following schedule forthe next sixweeks is given. p M ) ITEM LEADTIME (wxs) ON HAND LOT-SIZING RULE ‘ the Deluxe is processed through steps A5, A6, and A7. Both types finish at A8. The numbers
a z 5 mph-”40¢ ‘ in parentheses indicate the minutes it takes for that activity to process a single unit. i
S Lot»for-lot ‘ l
X Multiples of 25 l Stank"! l
W Multiples of 12
F Multiples of 30 1
K Lot»for-lot ‘ ‘
Q Multiples of 30
M Lot-for-lot ;
4' l 1
1 2 3 4 5 6 7 8
Gross requirements Deluxe
Schedule receipts
Projected on hand _ , . .
a) which step IS the bottleneck for the Standard products? Which step Is the bottleneck for
Net requirements
. the Deluxe products?
Planned order receipt , ‘
Planned order release b) What Is the capacity (measured as units per hour) of the facility to process the Standard
El products? What is the capacity to process the Deluxe products?
c) If 60% of the products are Standard and 40% are Deluxe, what is the average capacity
2. A firm makes car seats for an automaker in two varieties: leather and fabric. The standard 3 (measured as units pg, hour) of the facility?
labor-hours for these are 1.2 and 1.0 hours, respectively. The seats are made in two work d) Suppose the actual throughput of the facility is 32 units per hour. Again, 60% of the
l
l Page1 of2 510 Words [13 English (US) g __—+1oo%

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question