MAKE OR BUY DECISION - PROJECT MANAGEMENT QUESTION:


It cost the company $10,000 plus $100 per day to develop a product or they lease it for a cost of $250 a day. What is the breakeven point in days?

Top Answer

The way to approach this... View the full answer

Sign up to view the full answer

Other Answers

The correct answer is 67 days (66.66... View the full answer

BEP in case of producing a product is 100. BEP in... View the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online