The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying...

The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes.  The accompanying table shows the activities, time & sequence required:
Activity Immediate predecessor Time (weeks)
A --- 3
B A 2
C A 4
D A 4
E B 6
F C,D 6
G D,F 2
H D 3
I E,G,H 3
A.) What is the critical path?
B.) Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week.  Which would you shorten?
C.) What is the new critical path & earliest completion time? (from b's answer  I think)
Please solve using Microsoft Excel & show any work if possible.  Thanks!

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question