Consider the following information on job times and due dates. Determine the processing sequence using (1) FCFS, (2) SPT, and (3) EDD.

Consider the following information on job times and due dates. Determine the processing sequence using (1) FCFS, (2) SPT, and (3) EDD. For each sequencing rule, find the average job flow time and the average job tardiness.


Job Job Time (hours) Due Date (hours)
A 3.5 7
B 2.0 6
C 4.5 18
D 5.0 22
E 2.5 4
F 6.0 20

Sign up to view the entire interaction

Top Answer

Dear Student Please find... View the full answer

Business - 8217330.xls

FCFS
job
A
B
C
D
E
F EDD SPT
job days due date flow time tardiness
3.5
7
3.5
0
2
6
5.5
0
4.5
18
10
0
5
22
15
0
2.5
4
17.5
13.5
6
20
23.5
3.5
Average 12.5 2.83 job
B
E
A
C
D
F job days
2
2.5
3.5...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online