A construction project is broken down into 10 activities:

A construction project is broken down into 10 activities:

Activity - Immediate Predecessor - Time (Weeks)
1 - None - 4
2 - 1 - 2
3 - 1 - 4
4 - 1 - 3
5 - 2,3 - 5
6 - 3 - 6
7 - 4 - 2
8 - 5 - 3
9 - 6,7 - 5
10 - 8,9 - 7

a. Draw the network diagram.
b. Find the critical path.
Draw the network diagram.
b. Find the critical path.
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks?
Sign up to view the entire interaction

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question