A project for improving a billing process has the following precedence relationships and activity times:

A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A3 — B11 — C7 A D 13 B, C E10 B F6 D G5 E H 8 F, G b. Calculate the slack for each activity. Which activities are on the critical path?