SIGNAL-TEK CORPORATION Background Signal-Tek Corporation was founded in 1963. Following a series of new product developments, mergers, and...

SIGNAL-TEK CORPORATION
Background
Signal-Tek Corporation was founded in 1963. Following a series of new product developments,
mergers, and acquisitions, the company evolved into an $82.5 million corporation with wholly
owned subsidiaries operating in Colorado, Indiana, England, and Germany. The Denver division
generates approximately $30 million in revenues, primarily from signal generators. These
general-purpose test and measurement instrumentation products are used in a variety of industrial,
laboratory, and defense applications.
The Denver division had enjoyed several years of market leadership in these products
based on innovative design, low cost, and high product quality. However, in recent years, Signal-
Tek’s product brand recognition has begun to slip due to its inability to meet competition. Based
on timelier introduction of newer, low-cost products, two larger instrument manufacturers have
been taking some of the division’s market share. Signal-Tek has been unable to respond quickly
enough to these competitive pressures and, as a result, has had to reduce its work force by almost
15 percent recently It has become clear that the division must regain its market position by
refocusing on its goals of timely introduction of low-cost, solid-performance, high-reliability
instruments.
The Opportunity
In late July 2002, the U.S. Army released a request for sealed bid quotes on a new low-cost signal
generator that would eventually replace several thousand pieces of test equipment that the Army
had in the field. The company with the lowest unit cost for the instrument would get the award.
The division estimated that the design and testing requirements alone would cost between
$1 and $1.2 million and, based on the Army’s request, had to be completed within one year after
the release of the contract. The initial award included a first-year commitment of 900 units with a
second- and third-year requirement of an additional 900 units each year. These additional
requirements were to be awarded at a future date. Since the request also included an option to
double the requirements in each of years two and three, the contract could be worth 4,500 units
over the next three years with the potential of even more as the Army eventually replaced its
entire field stock.
In reviewing this request, the Denver division saw its opportunity to develop the most
utility/cost-efficient signal generator that had been built to date. However, given the potential
volume of product that was at stake, Signal-Tek also recognized that competition for the contract
could be very heavy. Marketing inquiries confirmed that the two competitors that had recently
been taking market share, plus one foreign competitor, were planning to bid the contract. The
division felt that the price of the unit would have to be under $1,900 in order to have a real
chance at winning the award.
The bids were to be opened by the Army on August 25, 2002. Thus, the division had only
enough time to make cost estimates based on current materials and labor standards used in similar
products, rather than on a detailed analysis of the new product design. Typically, the cost of the
division’s products was 50 percent materials and 50 percent labor and overhead. Costs, when
compared with the estimated required selling price, left a very low margin on the product.
However, the decision was made to proceed with the bid with the expectation that
somehow it would be possible to reduce the unit cost during the design and development stages.
The price for the first 3,600 units was established at $1,799 each, with a reduction in price made
available for units in excess of 3,600.
The Supply Management Environment
The supply department at the Denver division consisted of a supply manager named Barry Etcher
and a staff of five buyers—two senior buyers and three junior buyers. Although this staff had
experience in buying electronic components, neither Barry nor any of his buyers had any formal
engineering background. Therefore, the engineering staff rarely worked with the supply
management group during the design and prototype stages of new products. Typically, the supply
management group would become involved at the point just prior to the new product being turned
over to manufacturing for preproduction runs. By this time the design had been fairly well
completed, frequently requiring parts that were not currently used by the division. In addition, the
engineers had already spent a considerable amount of time talking with suppliers about new
products that were being developed by these potential suppliers and how these items might
enhance the new design.
After the Army reviewed the bids, Signal-Tek was awarded the contract. The division’s
management now had to focus on the issues of limited design time and the necessary cost
reduction programs.
1. How can early supply management involvement assist in low-cost and timely new
product development?
2. How does supply management’s involvement enhance an early supplier involvement
program? What are the potential benefits?
3. How can the division increase cooperation/communication between the engineering
and supply departments?
4. How will standardization improve the new product development process?
5. How does more effective supply management involvement change engineering’s
role?
6. What can the division do to help expand supply management’s contribution?
Dana Collins and Christine Childers developed this case under the direction of Professor David
N. Burt.
Sign up to view the entire interaction

Top Answer

Hi please... View the full answer

8525636.docx

1. Supply management is process that is related to the demand and supply network. It helps
in managing all the activities related to bringing the raw material and reaching the final
goods to the...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online