The project network for shooting a TV commercial as shown below has a fixed cost
of $85 per day, but money can be saved by shortening the project duration.
Activity
Predecessors
Normal Time
Crash Time (days)
Cost Increase (E)
(1st, 2nd, 3rd day)
A
7
4
25, 45, 65
B
12
10
55, 55
C
A
9
6
35,40, 60
D
A
11
9
30, 55
F
B. C
3
3
c) Draw either an activity on arrow network or an activity on node network to
represent the above project.
d) Using normal times calculate the minimum project completion time and
determine the critical path (s).
e) Which activities should be crashed to obtain the least cost schedule?
Find the cost of this schedule.

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask 0 bonus questions You can ask 0 questions (0 expire soon) You can ask 0 questions (will expire )
Answers in as fast as 15 minutes