A project has an initial requirement of $310,000 for fixed assets and $62,000 for net working capital.

A project has an initial requirement of $310,000 for fixed assets and $62,000 for net working capital. The fixed assets will be depreciated to a zero book value over the 3-year life of the project and have an estimated salvage value of $155,000. All of the net working capital will be recouped at the end of the project. The annual operating cash flow is $345,000 and the discount rate is 18 percent. What is the project's net present value if the tax rate is 34 percent?
1.  403618.02
2.  414141.41
3.  446047.36
4.  478122.21
5.  510197.06

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question