Use the project activity information presented below to complete this question.




Use the project activity information presented below to complete this question.

Task Predecessor Duration
A 5 days
B 7
C 4
D A 6
E B 9
F B 6
G C 4
H D,E 6
I D,E 8
J F,G,H 9
K I 10
L J,K 9

Assume that the project starts on 1/1/2010. Furthermore, assume a 7-day calendar. This means that there are no holidays or weekends, and that project tasks may fall on weekends or holidays.


Thanks

a. Manually create and present the activity-on-node network diagram.
b. Create and complete a table with 10 columns: Task Name, Duration, Start, Finish, ES, EF, LS, LF, Free Slack, and Total Slack. All dates should be specific calendar dates.
c. List all the critical paths.
d. How many days is the project duration

Sign up to view the entire interaction

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question