Over lunch, you and Mary meet to discuss next steps with the expansion project.

“Do we have everything we need on sales and costs?” you ask. ”It must be time to compute the net present value (NPV) and internal rate of return (IRR) of the Apix expansion project.”

“We have the data from James and Luke regarding projected sales and costs, respectively, for the food packaging project,” says Mary. “It is feasible to project that we will receive a tax break from this implementation. I have information from our audit firm that indicates that future depreciation methods for taxes will be straight-line; however, the corporate rates will be reduced to 35% as we assumed in our weighted average cost of capital (WACC) calculation.”

“That sounds good,” you say.

“Right," says Mary. "You can use a WACC of 10% for the computation of the NPV and comparison for IRR."

“I’ve got the information I need from Luke and James,” you say. "Does this look right to you? Here’s what they gave me,” you say, as you hand a sheet of paper to Mary.

“Let’s look at this now while we’re together,” she says.

The information you hand to Mary shows the following:

  • Initial investment outlay of $30 million, consisting of $25 million for equipment and $5 million for net working capital (NWC) (plastic substrate and ink inventory); NWC recoverable in terminal year
  • Project and equipment life: 5 years
  • Sales: $25 million per year for five years
  • Assume gross margin of 60% (exclusive of depreciation)
  • Depreciation: Straight-line for tax purposes
  • Selling, general, and administrative expenses: 10% of sales
  • Tax rate: 35%

You continue your conversation.

“It looks good,” says Mary. “Use this information from Luke and James to compute the cash flows for the project.”

“No problem,” you say.

“Then, compute NPV and IRR of the project using the Excel spreadsheet I sent earlier today,” says Mary. “Use the IRR financial function for the computation of IRR.”

“Okay,” you say. "I’ll submit my Excel file showing the computation of cash flows, NPV, and IRR by the end of week so you can look at it over the weekend.”

“Thanks,” says Mary.

Complete the above worksheet for this assignment.

HERE IS THE WORKSHEET 

FIN 615 NPV and IRR calculations Cost of Capital 10.00% Time/yr 0 1 2 3 4 5 Cash flow Input here Discounted CF 0 0 0 0 0 0 NPV 0 =cf1/((1+n)^1=cf2/((1+n)^2)=cf3/((1+n)^3)=cf4/((1+n)^4)=cf5/((1+n)^5) PV factor 0.909090909 0.826446281 0.7513148009 0.6830134554 0.6209213231 IRR Err:523
Background image of page 1
Sign up to view the entire interaction

Top Answer

Please find the... View the full answer

Copy of FINC615 NPV-IRR_IP_4.xls

FIN 615
NPV and IRR calculations Cost of Capital
Time/yr
Cash flow Input here
Discounted CF
NPV
PV factor
IRR 10.00%
0
1
2
3
###
9875000
9875000
9875000
30000000 8977272.727 8161157.0248...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online