Manson Construction Corp. has consistently used the percentage-of-completion method. In 2020, Manson started work

on a $10,500,000 construction contract that was completed in 2021.

The following information was taken from Manson's 2020 accounting records:


Billings to date $3,300,000

Costs incurred 3,150,000

Collections to date 2,100,000

Estimated costs to complete 6,300,000


Under the earnings approach, what amount of gross profit should Manson recognize in 2020 on this contract?

a. $525,000

b. $350,000

c. $1,050,000

d. $700,000

Top Answer

Hence, the... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question