This question was created from Module 1 Exam.docx https://www.coursehero.com/file/31503244/Module-1-Examdocx/

31503244-351576.jpeg

Select the correct statement about the Earned Value Management System (EVMS) Guidelines?

31503244-351576.jpeg

5) Which of the following statements is correct about the
relationship between technical performance and Earned Value Management (EVM)?
10129486 I 1 EVM performance data and technical performance do not deal with the
r same contract scope of work. Technical performance measures do not provide early warning of problems,
r whereas EVM data does.
Technical performance should not be considered in conjunction with EVM (-
analysis.
Technical Performance Measurement {TPM) analysis can give early warning
(3 of issues that might impact cost and schedule performance.

Top Answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question