Question

What is the management control point in a contractor's earned value management system (EVMS) at which earned value

management (EVM) data is developed and used to develop actions for cost and schedule variances, and to update estimates at completion (EACs)?

The lowest, most detailed level

The work package level

The control account level

The contractor does not provide EVM data based on WBS level

Top Answer

The management control point in a contractors earned value management system at... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question