Question 3: Project Crashing (21 marks)
a) Discuss the differences between CPM and PERT approaches for network analysis
Table 1
Activity
Predecessor
Normal
Crash
Normal
Crash
Crash
S
Time
Time
Cost ($)
Cost ($)
Cost/Day
(weeks)
(weeks)
($)
A
5
3
20 000
30 000
5000
B
2
10 000
20 000
10000
C
A
6
16 000
24 000
4000
D
A
6
3
25 000
43 000
6000
B
5
4
22 000
30 000
8000
F
B
7
4
30 000
48 000
6000
G
C,E
9
5
25 000
49 000
6000
H
D,F
8
6
30 000
44 000
7000
(b) Draw the above project network using the AON representation.
Determine the project paths and specify the critical path(s).
(d) Suppose that management wants to complete the project in 12 weeks to beat competition.
Which activities should be crashed, and for each crashed activity provide the total number of
weeks crashed and the total cost.
(e) What is the overall project crashing cost?

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask 0 bonus questions You can ask 0 questions (0 expire soon) You can ask 0 questions (will expire )
Answers in as fast as 15 minutes