Exercise d)
Develop an MRP record, similar to the one in figure 7, for wheat germ for the five weeks of
August. Wheat germ must be ordered in bulk-container quantities, so the planned orders must
be multiples of 2,000 pounds. Use a lead time of one week and an initial on-hand inventory of
3,184 pounds, assume that an order of 8,000 pounds is scheduled for receipt during Week 1.
Are there any weeks when you, as a planner, would consider planning an order above or below
the minimum required? Why? (Assume that there are no problems with storage capacity or
shelf life)

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask You can ask ( soon) You can ask (will expire )
Answers in as fast as 15 minutes