A simple project listing of five activities, their predecessors and their respective time estimates are presented below. Using the CPM, which

A simple project listing of five activities, their predecessors and their respective time estimates are presented below. Using the CPM, which activities have slack in this project?


Activity Predecessor Duration

A None 3

B A 2

C A 4

D B,C 4

E D 1

Top Answer

The network diagram shows us that the critical path is along... View the full answer

new imahe.png

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online