View the step-by-step solution to:

A network diagram is drawn using the Activity on Arrow (AOA) format. Find Earliest Start time, Latest Start time, Earliest Finish time, Latest Finish...

A network diagram is drawn using the Activity on Arrow (AOA) format.

Find Earliest Start time, Latest Start time, Earliest Finish time, Latest Finish time, and slack values for all activities.

 

                                               Immediate      Duration

Activity                                  Predecessors  (days)

a. organize layout team     -   5

b. organize modification team   -             3

c. design personnel jobs         a                     2

d. set machinery in place       b                     3

e. connect utilities                  c,d                  7

f. modify conveyor system    e                     4

g. train personnel                   e                     3

h. finishing touches                f                      5

i. run test lot                           g                     2

 


Q4.png

Q4.png

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question