In a job shop operations, four jobs may be performed on any of four machines.The hours required for each job on each machine are presented in the...

In a job shop operations, four jobs may be performed on any of four machines. The hours required for each job on each machine are presented in the following table. The plant supervisor would like to assign jobs so that total time is minimized. 

 

   MACHINE 

Job w x y z 

A 10 14 16 13

B 12 13 15 12 

C 9 12 12 11  

D 14 16 18 16


A. Find the best solution (by formulating it as an LP problem or any other method). Which assignments should be made? What cost?

B. Formulate this problem as a linear program.  

Top Answer

Job A should be assigned to machine Z Job B should be... View the full answer

2019-02-04 (1).png

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online