The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY

IMMEDIATE PREDECESSOR(S) A ---- B ---- C A, B D A E B F B G C H D, E, F I E J G, H K H, I The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 30 B 25 C 26 D 23 E 21 F 28 G 20 Prashant Tarun Page 1 H 27 I 22 J 30 K 25 a. Construct the project network diagram using Activity-on-Node (AON) approach. b. Determine the earliest start (ES) time, earliest finish (EF) time, latest finish (LF) time, and latest start (LS) time for all project activities. c. Determine slack times for all project activities. d. Identify the critical path(s) in the project network. e. How long will it take to complete the entire project?

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask You can ask ( soon) You can ask (will expire )
Answers in as fast as 15 minutes