Please solve the following problem related to Chapter 6 

1.     As part of a major plant renovation

project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:


Task

Duration (minutes)

Immediate Predecessor

A

0.3

-

B

0.5

A

C

0.4

B

D

0.5

-

E

1.7

D

F

0.8

C

G

1.2

E, F


How to do each of the following?


a.     Draw the precedence diagram.

b.    Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.

c.     Determine the minimum number of stations needed.

d.    Assign tasks to workstations on the basis of most following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

e.     Compute the percentage of idle time for the assignment in part d.

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask 0 bonus questions You can ask 0 questions (0 expire soon) You can ask 0 questions (will expire )
Answers in as fast as 15 minutes