Problem 5 (15 Points)
Below are the transaction records for eight weeks for to items. Item B is a component part of
Item A which is a finished product ready for retail sales. Both items are produced at Work
Center 101.
Item A
Ave. Processing Time/Unit at WC 101 2.1 hours
POQ = 5 weeks
Lead time = 2 weeks
Week
2
3
4
5
6
7
8
Gross requirements
2
24
3
5
1
3
4
50
Scheduled receipts
Projected available balance
28
26
2
13
8
7
4
0
0
Planned order releases
14
50
Component B
POQ - 5 weeks
Ave. Processing Time/Unit at WC 101 .6 hours
Lead time = 4 weeks
Week
2
3
4
5
6
7
8
Gross requirements
14
50
Scheduled receipts
14
Projected available balance
2
2
2
2
2
2
0
0
0
Planned order releases
A. Describe the impact that these items have on the capacity need of Work Center 101
over the eight week period. (10 Points)
B. What is the Low Level Code for Item B? (5 Points)

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Let our 24/7 Operations Management tutors help you get unstuck! Ask your first question.
A+ icon
Ask Expert Tutors You can ask You can ask ( soon) You can ask (will expire )
Answers in as fast as 15 minutes
A+ icon
Ask Expert Tutors