Mike's Wheel Factory makes bike wheels. The final product consists of 2 parts: rubber tires and metal

rims. The company has the following 2 operations:

(1)  the molding operation is where the metal rims are made. There are 8 machines, in which each machine produces 30 rims/hour, and operate for 8 hrs/day and 5 days/week.

(2)  the final assembly operation is where rubber tires are placed around each metal rim. There is 1 assembly line that can produce 250 rims/hour, and operates for 8hrs/day and 5 days/week.

Which operation should Mike's Wheel Factory decide to set total system capacity equal to?

Top Answer

Mike's wheel should decide to set... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question