Question

Process Information provided:

Operation A - design capacity 400 units/hr - planned utilization

80%

Operation B - (4 machines) design capacity 100, 80, 150, 125 units/hr - planned utilization 77%

Operation C - design capacity 350 units/hr - planned utilization 95%

Operation D - (2 machines) design capacity 190, 235 units/hr - planned utilization 72.5%


The sequence of flow is A -> B (any machine can be used if available) -> C -> D (any machine can be used if available). Calculate the overall flow rate for maximum (design) capacity and effective capacity.

Top Answer

Here is a detailed explanation... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question