An assembly line with 19 tasks is to be balanced. The longest task is 2.4 minutes, and the total processing time

for all tasks is 22 minutes. The line will operate for 410 net minutes per day. a) What is the minimum number of workstations needed if the output rate is to be 120 units per day?

Top Answer

7 workstations... View the full answer