Question 5: (2 points) The critical path for the network shown is: a-d-f-g b-e-f-g a-c-g a-d-h-i b-e-h-i Question 6:

Question 5: (2 points)


The critical path for the network shown is:



a-d-f-g

b-e-f-g

a-c-g

a-d-h-i

b-e-h-i

Question 6: (2 points)
Duration Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start U, V - - -
U W 35 50 65
V W, X 28 40 52
W Z 26 35 44
X Y 28 40 52
Y Z 26 29 38
Z End 36 60 84

What is the estimated expected (mean) time for activity Y?



38 days

35 days

29 days

30 days

26 days

Top Answer

Hello, We can only answer your free 3 questions per day one at a time. Please re-submit an individual question here:... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online