View the step-by-step solution to: Could you please answer questions 2, 5, 6, and 7? Thank you. 2.

This question was answered on Mar 25, 2011. View the Answer
Could you please answer Problems 2, 5, 6, and 7 for me? I've attached these questions. Also, I've included Chapter 10 (The Chapter the questions are from) just in case you want it. Thank you for your help.
Chapter 10 Problems 2, 5, 6, and 7.docx

Could you please answer questions 2, 5, 6, and 7? Thank you.
2. The new manager of the electric utility notes that recent summers have been warmer than average. Consequently, for next year she revises upward the probability that actual demand will exceed average demand; this is estimated to occur 8 percent of the year or roughly 29 summer days. She estimates that each power incident can cost far less than her predecessor had spent. Using different management techniques to deal with brownouts, she hopes to reduce the cost per incident to $10,000. Because the previous manager had not invested in additional capacity to cover maximum peak­load requirements, that option is still available. She faces the prospect that it will cost an extra $3,000,000 to increase capacity from average to peak. This amount is spread out over 10 years, or $300,000 per year.
Should peak­load capacity be installed?
5. Company capacity is 1 million units per year for a new food product. The sales force can sell 5 million units over a 5­year period, but only 100,000 in the first year. The breakeven volume is VBEP = 50,000 units with p = 3, vc = 2, and FC = 50,000. What is the situation? What recommendations do you support?
Using the QMpom module called Capacity Management Models (Breakeven) will facilitate solving the three (3) problems that are numbered 5 through 7.
6. The Global Company has engaged a management consultant to analyze and improve its operations. His major recommendation is to "conveyorize" the production floor. This would represent a sizable investment for Global.
In order to determine whether or not the idea is feasible, a breakeven analysis will be utilized.
The situation is as follows: The cost of the conveyor will be $200,000 to be depreciated on a straight­line basis over 10 years. The conveyor will reduce operating costs by $0.25 per unit. Each unit sells for $2.00. The sales manager estimates that, on the basis of previous years, Global can expect a sales volume of 100,000 units. This represents 100 percent utilization of capacity. Current yearly contribution to fixed costs is $100,000. Current vc rate is $0.50 per unit.
Should Global install this conveyor?
7. Zeta Corporation is considering the advantages of automating a part of its production line. The company's financial statement follows: Zeta Corporation
Total sales $40,000,000 Direct labor $12,000,000 Indirect labor $ 2,000,000 Direct materials $ 8,000,000 Depreciation $ 1,000,000 Taxes $ 500,000 Insurance $ 400,000 Sales costs $ 1,500,000 Total expenses $25,400,000 Net profit $14,600,000 The report is based on the production and sale of 100,000 units. The operations manager believes that an additional investment of $5 million can reduce the variable costs by 30 percent. The same output quantity and qualities would be maintained. Using 5­year straight­line depreciation of $1,000,000 per year, construct a breakeven chart. Based on the breakeven analysis, should Zeta introduce the automation? Just in case you want it here is Chapter 10. Some of the charts would not copy and paste correctly though.
Supply Chain Capacity Planning 10-1: Definitions of Supply Chain Capacity
Actual capacity of the supply chain is the greatest throughput rate that can be achieved with the existing configuration of resources and the accepted product or service mix plans. Altering the product or service mix can (and usually will) change actual realizable capacity. Modifying the existing configuration of resources, equipment, and people in the supply chain workforce alters real capacity. The systems point of view includes cash as part of the resources because cash can be converted into new machines, which alter real deliverable throughput capacity. The systems viewpoint includes good ideas, which can increase supply chain capacity with minimum expenditures.
The formula for actual measured capacity of the supply chain is
C = actual measured capacity (in units converted to standard hours)
T = real time available
E = efficiency
U = utilization

• Supply Chain Capacity Planning 10-1a: Standard Hours • T is determined by calculating the amount of time that is available when fully utilizing the resources that are already in place to make and deliver product throughput. Doubling the number of machines, trucks, etc., doubles the amount of available time, T. • E is the efficiency with which time T can be utilized to make and deliver different kinds of product. Then, T × E is equivalent to standard hours available to make and deliver the products. • U is how much of the available throughput capacity can be (or is) utilized. Lack of orders or breakdowns of productive systems diminish U. When T and E and U are multiplied, the product is C, the actual supply chain capacity that is being (or has been) utilized. • Table 10­1 illustrates the calculations. Table 10-1 Capacity Utilized (C) in Standard Hours of
PT •
• Assume that the supply chain is rated with a maximum capacity of 150 standard hours of throughput. It never achieves the maximum, but comes closest to doing so on Wednesday. There are a variety of reasons why the system does not achieve maximum throughput. Two factors embodied in E and U are explained later. Another reason could be that the system has bottlenecks and flow disruptions. • E, the efficiency, is a proportional factor used to convert units of throughput to standard times. Systems of machines and people that work slower have lower efficiency than those that have a higher productive output. Often, the best in the class is given an efficiency of one. It is to be expected that variations in efficiency will occur. Sometimes the source of the variation can be traced. If it is significant variation, then it should be corrected. Unexplained fluctuations in capacity are unpleasant and unprofitable. • If a supply chain is operating at 90 percent of the standard time because a supplier (somewhere along the supply chain line) has delivered defective product, remedial action must be taken with supplies on hand and the problem must be corrected with future deliveries. • U, the utilization, is applied as a proportional correction to standard time when there are supply chain disruptions. Even when everything is running as planned, the value of U is usually less than 100 percent. If the system is operating even faster, the value of U can exceed 100 percent. There are pros and cons related to running supply chains above maximum rated capacity. How long maximum capacity is exceeded also counts. • U is a measure to be wary of when it becomes an objective of management to keep it as close to 100 percent as possible. There are sound economic reasons not to operate supply chains above capacity. For example, stop production when the planned output quota has been met and safety stock is sufficient. Shutting down the production system for 2 hours of an 8­hour day means that the U measure goes to 75 percent. Actual measured supply chain capacity is going to be reduced by a fourth. • Management must establish the fact that supply chains are composed of complex subsystems some of which cannot function above capacity for very long. The costs of unsold throughput must be analyzed. How long will stored output remain as inventory? Are there fluctuations in demand that they will buffer or is the buffer in place already? The costs of arbitrary utilization of supply chain capacity to eliminate less than one hundred percent utilization should be recognized for what it is—waste of time and money due to fear of seeming to waste (unutilized) capacity. An appropriate decision model can be constructed to set proper supply chain throughput.
• As an example, assume that U is 0.963. This is likely to be viewed as a more reasonable utilization factor than 0.750. P/OM, in general, will not tolerate a permanent situation where utilization factors are below 0.900. Still, the target numbers will be dependent on the situation. For example, in service organizations, a value of U might be accepted to keep queues short. Cyclical supply chain demand systems can be expected to cycle between utilization factors in the 0.700 range and then up to more than 100 percent capacity. Cyclical industry companies prefer having excess capacity in reserve and expect to operate effectively below the misleading ideal of 100 percent utilization. • Using data in Table 10­1, the value of 130 actual standard hours of throughput, might have been obtained as follows: C = T x E x U = 150 x 0.9 x 0.963 = 130 actual standard

• The ratio of actual standard hours to maximum standard hours is equal to 130/150 = 0.87 or 87 percent. • Supply Chain Capacity Planning • A critical supply chain definition of capacity is related to containment. In fact, maximum capacity may be directly related to what can be maximally stored or contained somewhere along the supply chain route. Containment capacity takes many forms (i.e., the auditorium has a seating capacity of 360, the gas tank will hold 16 gallons, the restaurant freezer can store up to 40 meals in standard units). • Maximum supply chain capacity can also be defined as maximum sustained throughput of goods or services. Both meanings are regularly used by P/OM. The capacity to contain or store inventory is a well­received measure of capacity. Operations capacity describes how many units can be supplied per unit of time. For services, a bank might compare the maximum number of people the bank teller can process per hour with the maximum number of people the ATM can process per hour. This is a supply chain service capacity comparison. • For a manufacturing supply chain example, compare the maximum number of hot dogs Oscar Meyer can make and ship per hour with the maximum number of hot dogs Hebrew 10-1b: Maximum Rated Supply Chain Capacities National can make and ship per hour. In this supply chain the ingredients required to make the products have a flow through rate that must match the producers' rates.
• This comparison is one that both companies would like to make to compare their PMCs (productivities at maximum capacity). PMC makes an excellent benchmarking measure. In supply chain terms, benchmarking is a systematic comparison of fundamental measures with those of contestants performing similar supply chain functions. • Consider using maximum containments within the supply chain as a benchmarking measure. Generally, the larger the storage facility, the more material sitting around without having value added, and the poorer the performance measure. However, if a company built substantial petroleum storage facilities early in 1973, it would have been in the catbird seat when the oil embargo in the fall of 1973 created severe petroleum shortages. The harsh effects of the oil crisis lasted through the end of March 1974. • The utilization of supply chain containment capacity is an important factor for P/OM to consider. Having extra capacity would not have been a boon to Mobil Oil unless the tanks were filled with crudes and fuels. On the other hand, high utilization of containment capacity runs counter to the desire for low inventory levels, just­in­time deliveries, and constant value adding. • These two kinds of capacity situations have a trade­off relationship. Extracapacity and undercapacity within the supply chain are shown in Figure 10­1. When market demand falls below maximum supply capacity (MD < MSC), the production system can feed storage and build up inventories. When market demand exceeds maximum supply capacity (MD > MSC), the inventory can be used to help meet that demand. • The diagonal line in Figure 10­1 represents the maximum capacity to supply product. It is a rate of throughput that at the end of period T has the capability of producing S units. Realistically, the curved line is sometimes below the diagonal and sometimes above it. For convenience, the market demand rate over the entire period T accumulates total demand of S. Figure 10-1 Relationship of Variable Supply and Demand to Maximum Supply
Capacity • Difficult to Store Service Capacity • The concept developed here and shown in Figure 10­1 does not apply to services as readily as to goods being manufactured. This is because most services cannot be stored. The extracapacity on the left side of Figure 10­1 is wasted idle time for service personnel. For goods it can represent building stock on­hand that can be drawn down when the undercapacity, right side of Figure 10­1, occurs. • Backordering Augments Service Capacity • If the customer is willing, backorders can be used to satisfy demand when there is no inventory available. This applies to services that cannot be stored. It applies as well to the manufacturer who is out of stock. The overloaded system does not have to turn away orders if the customer agrees to wait until other customers' jobs are finished. • Supply Chain Capacity Planning • Another question about planning supply chain capacity is: "Should the maximum output capacity be great enough to handle peak load?" This is equivalent to providing enough electrical generating power to supply all needs for air­conditioning demand on extremely hot business days. Alternatively, should telephone companies have enough capacity to take care of all phone calls without any delays for Valentine's Day and Mother's Day? These holidays are known as the heaviest traffic days for phone companies. • The rule for putting peak versus nonpeak capacity into place is • Buy peak capacity when: Cp < Cnp • Cp is the extra investment required to assure peak capacity. In other words, it is the investment for peak capacity less that required to meet average demand, depreciated over the life of the system. Say it takes an extra $5,000,000 to increase capacity from average to peak. This amount is spread out over 10 years, or $500,000 per year. • Cnp is the cost of not having capacity to meet demands that are greater than the average demand. It is determined by the costs of such events as brownouts, power failures, loss of goodwill in the community, and there are lost revenues as well. Say that the total cost averages $30,000 per incident. • Figure 10­2 provides an illustration of the difference between peak and off­peak average demand, as well as the level of normal supply, which is above off­peak average in this case. Figure 10-2 Peak Supply Cannot Always Meet Supply Chain Demand 10-2: Peak and Off-Peak Supply Chain Demand •
• To illustrate with a case, assume that the probability that actual supply chain demand exceeds average demand is estimated to be 5 percent of the year or roughly 18 summer days. Total cost associated with Cnp is 365 x 0.05 x $30,000 = $547,500

• This is more than the investment to prevent any brownouts, so the best advice, based on these figures, is to buy the equipment to generate sufficient power to meet peak demands. • Supply Chain Capacity Planning 10-2a: Qualitative Aspects of Supply Chain Capacity
"As is our confidence, so is our
capacity." • —William Hazli
tt •
• If our confidence is high, so is our capacity. But this is a different definition of the word. Usually, when capacity is treated in a P/OM context, the quantitative point of view prevails. There are, however, qualitative aspects that are important to cite. • It is not unusual to hear "he or she has the capacity to be a fine ballplayer, chef, manager, …, etc." This invokes mental ability or physical skills. Organizations have capacities to deal with problems and opportunities. It is like an inventory of capabilities. Oftentimes, only when tested does the capacity to outperform the normal emerge. • Motorola developed the capacity to meet quality standards that are far superior to most other companies. Robert Galvin, former chairman of Motorola, challenged the company to develop peak capability for quality production. • The company had been embarrassed by the Japanese company Quasar's purchase of its TV division, which had a history of severe defectives—reporting between 150 and 180 defects per 100 sets. Within three years, traditional Japanese quality had asserted itself. The defect rate had dropped to 3 or 4 per 100 sets. Service calls dropped from $22 million to less than $4 million. In­plant repair staff went from 120 to 15. Quality people liked to tell the story. Galvin did not like to hear the story and threw down the gauntlet. • Motorola has since become a world leader in the production of quality products. Motorola set for itself a difficult quality goal of 3.4 defects per million parts. This is associated with (modified) six­sigma limits as compared to three­sigma limits in quality control (see Spotlight 7­2). Motorola was the first company to win the Baldrige Award for quality ability. • Skillful management can increase the level of capacity that is achieved. Managing installed physical capacity properly means obtaining the maximum available capacity. This goal is particularly relevant when dealing with management of peak demand. If the maximum capacity of the process is less than the peak demand, knowing how to assign priorities will influence real capacity levels achieved. • Supply Chain Capacity Planning • Capacity as measured by maximum output volume per unit time, or throughput rate, comes closest to capturing the P/OM concept. That does not make it easy to measure. It is possible to produce at more than 100 percent of capacity for a period of time. Maximum capacity depends on who is doing the work and what is being made or serviced. Although 100 percent and maximum capacity are illusive concepts, they are useful standards to go by as long as the users are aware of their arbitrary nature. • When people are part of the process, some of the qualitative aspects of capacity cannot be ignored. Some people work faster than others. Most people fluctuate in their rates of output. There is a learning curve at work. People learn from practice how to do a better job. Some people can learn faster than others. Individuality allows some people to do certain jobs better than others. In this regard, all people are not alike. Ambiguity, opportunity, and challenge abound in this arena. 10-2b: Maximum Supply Chain Capacity—100 Percent Rating • Machines work at different speeds. NASCAR drivers illustrate that point. Different velocities are best for optimal fuel consumption, minimum tire wear, and life of the car. Machines can be set for certain speeds that engineers would say are equivalent to 100 percent of their capacities. Ask the engineer what will happen if the machine is set to work faster. A typical answer will be that the machine will wear out sooner. • Figure 10­3 shows two patterns that are typical of wear­out life and failure as a function of accumulated usage and age. Pattern A illustrates the diminishing output lumens of a lightbulb before final failure. Pattern B shows a Weibull­type distribution, which reflects the high initial mortality of certain products (such as lightbulbs). Then there is a period of low product mortality until it reaches the expected time of failure. Time­of­failure distributions must be understood if capacity is to be managed properly. Figure 10-3
Wearout and Failure Patterns as a Function of Accumulated Usage and Age—The Failure
Distribution (Pattern B) Is the Weibull Distribution •
• Setting standards for maximum output capacity creates an interesting comparison between what people and machines can do. For highly repetitive jobs, most machines can be set to work faster than people. For heavy and difficult work, especially in environments that are very hot, noisy, and even life threatening, machines win without question. Thus, robots are the best choice for nuclear experimentation. Also affecting the determination of capacity is the fact that machines can break down and people can be absent. Maximum capacity is usually determined with all the systems on go. • On the other hand, automated voice mail systems are tedious, although improving. They can require listening to endless options. It is not unusual to have to listen to seven or eight alternatives before getting to the one that applies. It is generally faster, and more gratifying, for the customer to speak to an operator but it is more costly. • Capabilities and capacities of automated systems are improving. The bank teller can perform transactions that ATMs cannot handle but for routine requests ATMs are faster and cost less. Especially with services, capacity measures are a function of the kinds of demands on the systems. Excess demand tends to deteriorate the performance of service systems. Requirements for special services that are common in many systems such as health care and education also make it difficult to establish maximum capacity figures.
Capricious Demand •
• Capacity planning is one of the most important business activities. It is filled with opportunity to manage to advantage and fraught with difficulties. This is especially true if demand is capricious and tough to forecast correctly. Capacity planning is done to reach optimal supply decisions that, it is hoped, will match future demand patterns. This means that capacity planning does not have to be a single frozen value but can be a dynamic trajectory with fluctuations and oscillations. Hackers enjoy swamping server capacity and succeed in bringing systems down. Innocently, the first weekend that the iPhone was sold resulted in so many requests for service that Skype was out of service for many hours. • Supply Chain Capacity Planning • There are two aspects to capacity requirements planning (CRP) . The strategic issues related to long­term planning including breakeven concepts and breakeven points and optimal allocation of resources are being treated in this chapter. The shorter­term, tactical issues are operating issues that properly belong to a discussion of material requirements planning. The ability to alter supply chain capacity in steps or stages, as shown in Figure 10­4, is valuable for strategic plans to meet a longer­term goal. Figure 10-4 Dynamic 10-2c: Capacity Requirements Planning (CRP) Adjustment of Maximum Supply Chain Capacity •
• It takes planning to keep as flexible as possible with respect to supply chain capacity. Combinations of negotiations (as in a power grid) and technology can be brought to bear on a temporary basis. Consider the use of leases and rentals: • Part­time employees are a familiar means for making capacity adjustments, up or down. They do not require either severance pay or fringe benefits. Part­time employees relieve the firm of many other obligations associated with full­time employees. Rentals are an equivalent method for making capacity adjustments with equipment and space without taking on long­term commitments that lock the company into higher capacity than it is likely to need over the long term. • Coproducers and copackers are firms used to increase supply by subcontracting with them on a short­, medium­, or long­term basis. For example, a company that sells margarine might make enough to supply 60 percent of its market. The rest of its market demand is supplied by the output of a coproducer that has excess capacity. The product of the coproducer is packed in the subcontracting company's familiar package. • upply Chain Capacity Planning • Capacity planning for important elements within the total supply chain is often constrained to an optimal size by the engineering requirements of the process. Many chemical processes must be designed and built to a specific size in order to operate properly. Glass windshields require production steps requiring exact amounts of time. 10-3: Upscaling and Downsizing Supply Chain Capacity Capacity decisions concern how to meet peak demand and yet not have too much in reserve for
off-peak times. The capacity of the dam and the transmission lines carried by the towers all play a
part in this energy supply chain. • © 2008 Jupiterimages Corporation • Serialized flow shop processes also are constrained by engineering factors, although to a lesser extent than continuous chemical flow process. Job shop and batch processes are far more flexible with regard to optimal production volume sizes. • To increase maximum capacities, processes can sometimes be operated above their rated capacities by using overtime and faster conveyor speeds. There are quality repercussions and the equipment is seldom designed for sustained overloads. • To meet greater demand, it may be advisable to subcontract with coproducers until such time that additional demand warrants building another plant. Coprocessing does not have the flexibility of batch shops, which can be expanded and contracted within limits. • As the labor component of the process changes, the capacity adjustment reflects this fact, allowing an increase or decrease in the workforce. Because many services are notable for their labor percentage of the cost of...

This is the end of the preview. Download to see the full text
Sign up to view the entire interaction

Top Answer

Dear Student, PFA Revised Solution. The company has contribution of $1.50 per unit or $150,000 in total. After... View the full answer


Could you please answer questions 2, 5, 6, and 7? Thank you. 2. The new manager of the electric utility notes that recent summers have been warmer than average. Consequently, for next year she...

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors and customizable flashcards—available anywhere, anytime.


Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access or to earn money with our Marketplace.

    Browse Documents
  • 890,990,898

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
  • 890,990,898


    Browse existing sets or create your own using our digital flashcard system. A simple yet effective studying tool to help you earn the grade that you want!

    Browse Flashcards