ISE 514 HW #9 1. The table below describes the elements of a project Task Predecessors Duration A none 5 B none 9 C none 8 D A 6 E A 10 F C 7 G B,C,D...

How to solve the this question?

ISE 514 HW #9 1. The table below describes the elements of a project Task Predecessors Duration A none 5 B none 9 C none 8 D A 6 E A 10 F C 7 G B,C,D 3 H C,D,E 12 I E,G 8 J B,D,F 10 a. Draw a network representation of the project elements. Represent the activities on the arcs of the networks. (20 points) b. Calculate the length of the critical path. (10 points) c. List the critical activities. (10 points)
Background image of page 1
Sign up to view the entire interaction

Top Answer

Dear Student Please find... View the full answer

Operations Management  - 8194358.doc

ISE 514
HW #9
1. The table below describes the elements of a project Task Predecessors Duration
A
none
5
B
none
9
C
none
8
D
A
6
E
A
10
F
C
7
G
B,C,D
3
H
C,D,E
12
I
E,G
8
J
B,D,F
10
a. Draw a...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online