Consider the following network for conducting a two-week (10 working days) computer training class: 2 B A 3 7 1 4 E 5 2 C D 6 3 3 Act. Duration ,...

Consider the following network for conducting a two-week (10 working days) computer training class:




Activity Crash time (days) Crashed costs (total) Normal Time (total) Normal Costs
A 4 $800 7 $500
B 2 350 3 200
C 4 900 6 500
D 1 500 3 200
E 1 550
2 300
$3100

a-) Indirect costs are $75 per day. Using the information generated in problem 31, plot the Total time-cost tradeoff for the project in the figure 2, below.
31. Consider the following network for conducting a two-week (10 working days) computer training class : 1 2 4 3 5 A 7 B 3 D 3 C 6 E 2 Act. Duration, days Key Activity Crash time (days) Crashed costs (total) Normal Time (total) Normal Costs A 4 $800 7 $500 B 2 350 3 200 C 4 900 6 500 D 1 500 3 200 E 1 550 2 300 $3100 a-) Indirect costs are $75 per day. Using the information generated in problem 31, plot the Total time-cost tradeoff for the project in the figure 2, below. 1
Background image of page 1
Sign up to view the entire interaction

Top Answer

We can only answer your free 3 questions one at a time. You have two options to get your questions answered:... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online