The activities of a project and their time estimates are given below :

The activities of a project and their time estimates are given below :
Activity Estimated duration of activity (in weeks)
Optimistic time (to) Most likely time(tm) Pessimistic time (tp)
1-2 2 5 8
1-4 4 19 28
1-5 5 11 17
2-3 3 9 27
2-6 3 6 15
3-6 2 5 14
4-6 3 6 15
5-7 1 4 7
5-8 2 5 14
6-8 6 12 30
7-8 2 5 8
a) Draw the PERT network Diagram
b) Determine the mean time and standard deviation of each activity
c) Determine the critical path and the standard deviation for the critical path
d) Calculate the slack for the events
e) Calculate the total float, free float and independent float for each activity

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question