See attached:

a. Construct the appropriate network diagram
b. Indicate the critical path
c. What is the expected completion time for the project?
d. You can accomplish any one of the following at an additional cost of $1,500
(1) Reduce Job 5 by two days
(2) Reduce Job 3 by two days
(3) Reduce Job 7 by two days
If you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose and why?
e. What is the probability that the project will be completed in 30 days?
3.a Times (Days) Job Number Predecessor Jobs a m b 1 - 2 3 4 2 1 1 2 3 3 1 4 5 12 4 1 3 4 11 5 2 1 3 5 6 3 1 2 3 7 4 1 8 9 8 5,6 2 4 6 9 8 2 4 12 10 7 3 4 5 11 9,10 5 7 8 a. Construct the appropriate network diagram b. Indicate the critical path c. What is the expected completion time for the project? d. You can accomplish any one of the following at an additional cost of $1,500 (1) Reduce Job 5 by two days (2) Reduce Job 3 by two days (3) Reduce Job 7 by two days If you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose and why? e. What is the probability that the project will be completed in 30 days?
Background image of page 1

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question