The following represents a project that should be scheduled using CPM:

The following represents a project that should be scheduled using CPM:
TIMES(DAYS)
ACTIVITY IMMEDIATE PREDECESSORS a m b
A 1 3 5
B 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C,D 3 4 5
II'
G D, E 1 4 6
H F,G 2 4 5
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?

Sign up to view the entire interaction

Top Answer

Here is the explanation for... View the full answer

8547589.xlsx

Project Management Precedences; 3 time estimates Enter the times in the appropriate column(s). Enter the precedences, one per column. (Do not try to use
commas). Data
Activity
Optimistic Likely...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online