Question

<ol><li>what would be the best Gantt chart for the following tasks?</li><li>how the best

work breakdown for the following tasks?</li><li><br /></li><li><img src="/qa/attachment/8934878/" alt="Screen Shot 2019-07-30 at 9.05.41 PM.png" /></li></ol>

Screen Shot 2019-07-30 at 9.05.41 PM.png

Project 112 days Initial Study 10 days
Study Existing System 3 days
Carry Out |nterview(s) 2 days
Prepare Documentation 1 wk Feasibility Study 19.5 days
Identify Problems 5 days
understn and Analyse Problems 3.5 days
Estimate Project Cost 5 days
Assess Project Risk 2 days
Propose Solution 3 days
Task Scheduling 1 day
Deliverable to Project Manager 0 days Requirement Analysis 15.5 days Investigate Current Environment 1.5 wks
Investigate and Define Requiremer8 days Requirements Specifications 23 days
Prepare Specifications 6 days
Prepare Use Case Diagram 6 days
Prepare Data Dictionary 6 days
Prototyping 1 wk System Design 8 days
Design New System 6 days
Design Test Plan 16 hrs Coding &amp; testing 24 days
Coding 2 wks
Unit Testing 2 wks
Integration Testing 3 days
Update Data Dictionary 8 hrs System Testing 12 days
Hardware &amp; System Testing 3 days
Acceptance Testing 3 days
Prepare Documentation 6 days Deliverable to Project Manager 0 days

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question