1.     For a project, the expected project completion time and its variance have been estimated as

Te = 90 days, and Ve = 19.44. Compute the following:

(a) the probability that the project can be completed in 88 days:


Z = -.45 so the probability is


(b) the probability that the project can be completed in 92 days:


Z = .45 so the probability is

(c) the probability of completing the project between 88 and 92 days inclusive:



(d) how far ahead the project should be started for a 0.995 probability of completing by the deadline.

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question