Question

I do not know how to start and complete the attached Earned Value. Any assistance will be greatly

appreciated.

EVM 13.3_Page_2.jpgEVM 13.3_Page_1.jpg

EVM 13.3_Page_1.jpg

Exercise 13—3
Basic Performance Measurements Instructions: 1. Determine the Budget Baseline (BCWS) and Earned Value (BCWP) by period for each
work package and control account. Calculate the total of the six measurement periods in the
right total column. The total of the six periods for both the Planned Baseline (BCWS) and
Earned Value (BCWP) must equal the budget (BAC) for the work package. The symbols in
the schedule represent: 0 = Planned Earning Point A = Planned Milestone
9 = Completed Earning Point V = Completed Milestone Calculate lhe period by period totals for the Planned Baseline (BCWS) and Earned Value
(BCWP) both on a current period basis (Cur) and cumulative period by period basis (Cum). Calculate Cost Variance (CV) and Schedule Variance (SV) for each period based on the Planned Baseline (BCWS), Earned Value (BCWP), and Actual Cost (ACWP) totals. Calculate
both current period (Cur) and cumulative period by period (Cum) variances. 4. Analyze the calculated variances and be prepared to discuss them. 627—13-35

EVM 13.3_Page_2.jpg

Exercise 13-3
Basic Performance Measurements
Measurement Periods
Budget
Performance
Control Account/Work Package
(BAC)
Earning Method
Measure
2
3
4
5
6
Totals
2.1.3 Customer Service Solution Design
2.1.3.1 Management Structure Design
10
0%/100%
Planned (BCWS
Earned (BCWP)
2.1.3.2 Customer Service Rep Role Description
20
40% /60%
Planned (BCWS
Earned (BCWP)
10% 4
40% 4 40% 4 10%
2.1.3.3 New Customer Business Process Design
30
Milestone
Planned (BCWS)
Earned (BCWP)
40%
30% <30%
2.1.3.4 Service Order Business Process Design
30
% Complete
30%
50%
20%
627-13-36
Planned (BCWS)
Earned (BCWP)
Apportioned
2.1.3.5 Supervision & Review
20
(Based on Work
Apportioned Effort - Ratio 1/3 of Planned &
Packages 2.1.3.3 Planned (BCWS)
Earned for 2.1.3.3 & 2.1.3.4 Combined
& 2.1.3.4)
Earned (BCWP)
2.1.4 Project Management
12
Level Of Effort
Planned (BCWS)
Earned (BCWP)
Cur Cum Cur Cum Cur Cum Cur Cum Cur Cum Cur Cum
Totals
122
Planned (BCWS)
Earned (BCWP)
Actuals (ACWP) 14 14 24 38 26 64 26 90 20 110 18 128
Cost Var (CV)
Sched Var (SV)
Legend:
- Planned Earning Point
- Planned Milestone
- Completed Earning Point
- Completed Milestone

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask 0 bonus questions You can ask 0 questions (0 expire soon) You can ask 0 questions (will expire )
Answers in as fast as 15 minutes