Question


27.

A critical path within a project network is defined by that path that has the greatest

slack times for each of the activities.


-True

-False


28.

In a project network, slack associated with an activity can be calculated by subtracting the latest the activity can finish from the latest it can be started.


-True

-False


29.

When a client requires that a project must be outlined in a specific way, this is an example of a project ______________ .


-statement

-constraint

-requirements

-necessity


32.

Because on-time completion of a project is so important, monitoring usually focuses only on the project schedule.


-True

-False


33.

Schedule Variance in dollars is the difference between what was planned to be spent (Planned Value) at a specific point in the schedule and what was actually earned (Earned Value) for that period.


-True

-False

Top Answer

27 False; Thecritical pathis thepaththrough theproject network inwhich none of theactivities have slack. 28... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question