Question

A software company has received a contract from a client for the development of an

E-Auction system. A team of engineers has determined the activities, precedence constraints and time estimates as given in the table below. All times are in weeks.

Capture.JPG


(a) Draw an activity on arrow (AOA) network to represent this project. (5 marks)

(b) Complete the expected time for each activity of the project. Determine the critical path(s). What is the expected project completion time and its variance? (4 marks)

(c) Calculate the free float for each non-critical activity. (2 marks)

(d) What is the probability that the project will be completed within 24 weeks (1 mark)

(e) By what date is management 96 percent sure completion will occur?

Capture.JPG

Step-by-step answer

The student who asked this found it Helpful

ipiscing elit. Nam

s ante, dapibus a molestie consequat, ultrices ac magna. Fusce dui lectus, congue vel laoreet ac, dictum vitae odio. Done

fficitur laoreet. Nam risus ante, dapibus a molestie consequat, ultrices ac magna. Fusce

or nec facilisis. Pellentesque dapibus effic

ctum vitae odio. Donec aliquet. Lorem ipsum dolor sit a

icitur laoreet. Nam risus ante, dapibus a molestie consequat, ultrices ac magna. Fusce dui l

o. Donec aliquet. Lorem ipsum

ur laoreet. Nam risus ante, dapibus a molestie consequat, u

acinia pulvi

16_6_1.1.JPG16_6_1.jpeg

16_6_1.1.JPG
r

Subscribe to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Let our 24/7 Project Management tutors help you get unstuck! Ask your first question.
A+ icon
Ask Expert Tutors You can ask You can ask You can ask (will expire )
Answers in as fast as 15 minutes