Question

a)     Sketch AON (5 Marks)b)     Sketch PERT (10 marks)

c)     Mention Critical Path Activities (1 mark)

Calculate the project variance. Keep two decimals. (3marks)

below image is question

PHOTO-2020-07-15-11-09-45.jpg

Image transcriptions

ERM) [Compatibility Mode] - Word Table Tool: Home Insert Design Layout References Sign in Mailings Review View Help Design Layout Tell me what you want to do TITLE Share Title TITLE TITLE nu Title A 5/Paragraph Spacing . CONs Fonts Effects . Set as Default Watermark Page Page Document Formatting Color . Borders Page Background b) Sketch AON (5 Marks) c) Sketch PERT (10 marks) d) Mention Critical Path Activities (1 mark) e) Calculate the project variance. Keep two decimals. (3marks) Activity Predecessor Time in Weeks Duration Variance Optimistic (a) |Most Probable (m) Pessimistic (b) T- (a + 4m + b) /6 6=(6-2)/6 A 2 4 B C D A 3 6 E B 2 F B G C H C I F. G J H 6 K D. E L F.C 2 M K L 4 100% N I J 6 11:09 AM 2020-07-15 of 2 332 words English (Canada) W Type here to search a

Answered by Expert Tutors
Step-by-step explanation
3 Attachments
Screenshot 2020-07-16 at 12.44.16 AM.png
png
Slide1.jpeg
jpeg
Slide2.jpeg
jpeg
ERM) [Compatibility Mode] - Word Table Tool: CONs Fonts Effects . Set as Default Watermark Page Page Document Formatting Color . Borders Page...
Get unstuck

311,847 students got unstuck by Course
Hero in the last week

step by step solutions

Our Expert Tutors provide step by step solutions to help you excel in your courses