1.      When planning for a distributed Program Increment (PI) Planning

event with a large difference in time zones, what are two key preparation and facilitation focus areas for a Release Train Engineer (RTE)? (Choose two.)


a)      Adjust the PI agenda to 2.5 - 3 days, allowing for overlapping hours
b)     Arrange and test presentation audio and video connectivity in all locations
c)      Have a single RTE and technical support person that acts as a central point of communication for all locations
d)     Split up the PI Planning event per time zone and then have the final plan review, confidence vote, and planning retrospective as one centralized meeting
e)      Share the outcomes of preparation meetings with local Scrum Masters so they can arrange local rooms

Answer & Explanation
Verified Solved by verified expert

entFusce dui lectus, congue vel laoreet ac, dictum vitae odio. Donec aliquet. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam lacinia pulvinar to

oultrices ac magna. Fusce dui lectus, congue vel laoreet ac, dictum vitae odio. Donec aliquet. Lorem ipsum dolor sit

nec facilisis.

Unlock full access to Course Hero

Explore over 16 million step-by-step answers from our library

Subscribe to view answer