In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's...

1.    In the following table the activities with their precedence sequence and expected​ time​ (days) are listed for a project on which​ Carl​ Betterton's construction company​ is​ working:

Activity Immediate Predecessors Time (days)

A - 5

B A 4

C A 6

D B 6

E B 4

F C 4

G D 6

H E, F 8

 

​Carl's team should be able to complete the project in____________days.

 

Critical path activities​ for​ Carl's project are_____ -_______  -_________-________

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question