A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below:

4. A small software development project at​ Krishna​ Dhir's firm has five major activities. The times are estimated and provided in the​ table​ below:


Activity Immediate Predecessors A M B

A - 2 5 8

B - 3 6 9

C A 4 7 10

D A 2 5 14

E B 3 3 3


​​a) The expected completion time for this project is ____________

​​b) The project variance value of completion time is ____________

Top Answer

a. The expected completion time... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online