Next THREE questions are based on the following information The expected number of days to completion for a different project is 3.85 days, E(x) =...

Next THREE questions are based on the following information The expected number of days to completion for a different project is 3.85 days, E(x) = 3.85, with a variance of 1.35, var(x) = 1.35. The project cost is made up of a fixed cost of $50,000, plus $8,500 for each day taken to complete the project.   

11 The expected value of the project cost is: a $84,360 b $83,815 c $83,270 d $82,725

12 The variance of project cost is: a 97537500 b 85172400 c 61475 d 11475

13 The standard deviation of project cost is: a $107.12 b $247.94 c $9,228.89 d $9,876.11

14 In a binomial distribution, the trial in the random experiment is repeated 60 times and the probability of success is 0.45. The expected number of successes is, a 27 b 29 c 31 d 32

15 In the previous question the variance of the number of successes is: a 13.65 b 14.85 c 15.25 d 16.15

16 If you toss a balanced coin 40 times, the probability of getting 20 tails is: a 0.1254 b 0.1881 c 0.2821 d 0.5

17 If you toss a balanced coin 40 times, the expected number of tails is, a 22 b 20 c 18 d 16

Top Answer

11) d $82,725 12) a 97537500 ... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online