A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below:

A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below:

Activity --------Immediate Predecessor -------a---------m-------b

A----------------- --------- ----2------- 5 -----8

B----------------- --------- ----3------- 6 -----9

C----------------- A -----4----- 7 -----10

D----------------- B ----2------- 5 -----14

E----------------- C ----3------- 3 -----3

The expected completion time for this project is ______(Whole Number)

The project variance value of completion time is ____ ( Whole Number)

Top Answer

Expected time of completion=15... View the full answer

ADA67F0D-3FF6-4E36-9BCA-31D1864EBE84.jpeg

Sign up to view the full answer

Other Answers

a) T he expected completion time for... View the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online