Using the following project outline for problems 33-35
Immediate
Task
Predecessor
Task Length (Days)
A
2
B
C
A
D
B
E
C. D
5
F
C. D
G
E. F
7
H
E. F
4
33) What is the critical path?
A. A-B-D-E
B. B-C-E-F
C. B-D-F-G
D. A-D-G-H

Top Answer

The way to answer this question is ... View the full answer

UI.jpeg

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question